The Kanpur-Lucknow Expressway on NH-27 is set for expansion to eight lanes, with the NHAI acquiring most of the 63 km stretch needed for this upgrade. Construction of the expressway, currently at 50% completion, aims for a June 2025 finish.
Presently, the 75 km journey from Kanpur to Lucknow takes four hours due to construction-related diversions and narrow roads causing significant traffic jams. The situation is worsened by trucks and cargo vehicles from Bundelkhand to Lucknow. NHAI officials state that upon completion, the expressway will reduce travel time to 35-45 minutes.
Also Read:Delhi: Innocent Child’s Body Scarred By Cigarette Burns, Murdered And Dumped In Toilet
Route
The expressway will run from Shaheed Path in Lucknow through Banthra, Bani, Datoi, Kantha, Taura, Neora, Amarsus, to Azad Chauraha.
Key Points
- 63 km six-lane under construction, land acquired for future expansion.
- Completion targeted for June 2025, connecting to Azad Marg Ring Road.
- Current travel time of four hours from Lucknow, expected to reduce to 35 minutes.
- Features include three large bridges, 28 small bridges, and six flyovers.
Also Read:Bengaluru Hospital Left 2-Inch Needle In Spine During Surgery, Woman Gets Justice After Two Decades
As of last week, 50% of the construction on the expressway has been completed.